A power purchase agreement locks your company into buying clean power, or its financial equivalent, for 10 to 20 years. The commercial team usually focuses on the price. Your job as in-house counsel is everything else: which structure fits your market, which risks you’re actually taking on, and how you’ll keep control of the contract until 2045.
This guide covers how to choose between a physical and a virtual PPA, how to negotiate the clauses that move risk between you and the developer, and how to manage the obligations once the deal is signed.
Key takeaways
- Pick the structure first: A physical PPA generally requires your load to be in the same competitive market as the project. A virtual PPA can support procurement across different markets, including regulated utility territories, but usually requires an ASC 815 derivative assessment.
- Price is only half the deal: Escalators, floors, caps and the settlement point decide how much risk you actually carry.
- Spend your redline time on 4 clauses: curtailment, change in law, credit support and RECs. That’s where money and liability move.
- Plan your exit before you need it: Termination payments in a VPPA can be large, so negotiate assignment and buyout rights up front.
- Manage the PPA for the full 10 to 20 years: Key dates, an owner for each obligation and amendments stored with the master agreement keep you in control after the deal team moves on.
What is a power purchase agreement?
A power purchase agreement (PPA) is a long-term contract in which a buyer, the offtaker, agrees to purchase electricity from a specific generating project at a negotiated price. The contract may also provide for the transfer of associated renewable energy certificates (RECs). Corporate PPAs typically run 10 to 20 years and help finance new wind, solar, storage, or other clean power projects.
PPA agreement” is a redundant way to refer to a power purchase agreement. The term covers two very different legal instruments, though, and that’s where your work starts.
The market is large and concentrated. According to BloombergNEF, corporations announced 55.9 GW of clean power PPAs in 2025, with a record 29.5 GW in the US. The same report found that the number of unique US corporate buyers fell 51% to just 33, as Big Tech signed most of the deals. If you’re not a hyperscaler, you may be negotiating against developers with substantially more experience closing these deals. Your term sheet needs to be sharp.
How to choose between a physical PPA and a virtual PPA
Your first decision when structuring a power purchase agreement is which type to sign. The right choice depends mostly on where your load sits. Get this wrong, and the rest of the negotiation doesn’t matter.
How a physical PPA works
In a physical PPA, you take delivery of the electricity and the RECs at an agreed delivery point. You pay the contract price for each MWh the project generates, then the power flows through the grid to your sites.
The catch is geography. Under the US EPA’s green power guidance, physical PPAs by non-utility buyers are generally only possible in competitive electricity markets, and the project and buyer must sit in the same power market. In practice, a retail electricity provider often “sleeves” the power to your meter, which adds a third contract to manage.
How a virtual PPA works
A virtual PPA (VPPA), also called a financial PPA or contract for differences, never delivers a single electron to you. The project sells its power into the wholesale market at the floating price. You and the developer then settle the difference against a fixed strike price.
- Market price below the strike price: you pay the developer the difference.
- Market price above the strike price: the developer pays you.
- RECs: usually transferred to you under the contract, which supports renewable claims.
Because nothing is physically delivered, a VPPA can let you procure power from a project in a different market, including when your sites are in regulated utility territories, subject to the applicable market rules and contract structure. That flexibility is a major reason many multi-site buyers choose a VPPA.
It also raises questions that a physical deal does not. Your accounting team will need to assess whether the VPPA is a derivative under ASC 815, which may create mark-to-market swings in earnings. Your counsel should also check whether the contract raises questions about swap reporting under the Commodity Exchange Act. Bring finance and treasury in before the term sheet goes out.
Physical vs virtual PPA at a glance
| Factor | Physical PPA | Virtual PPA (VPPA) |
|---|---|---|
| Power delivered to you | Yes, at an agreed delivery point | No, power is sold into the wholesale market |
| Where your load can be | Same competitive market as the project | Different markets, including regulated utility territories, subject to applicable rules |
| RECs | May be transferred with the power, depending on the contract | Usually transferred separately |
| Main price exposure | Contract price plus delivery and sleeving costs | Difference between the strike price and the market price |
| Basis risk | Lower because the delivery point is defined | Higher because the settlement hub and project node can diverge |
| Accounting review | Often treated as a supply contract | Usually requires a derivative assessment under ASC 815 |
| Extra contracts | Sleeving or retail supply agreement | Your existing utility supply stays separate |
How to pick a PPA pricing model
Price is the commercial team’s headline number. The structure around it decides how much risk you’re really buying.
- Fixed price: one price per MWh for the whole term. This provides maximum budget certainty, but you may overpay if market prices fall.
- Escalating price: a fixed starting price that rises by an agreed percentage each year. Model it over the full term, because small escalators compound.
- Floors, caps and collars: limit settlement payments in either direction. In a VPPA, negotiate carefully how each one affects your downside when wholesale prices fall.
- As-generated vs shaped volume: as-generated means you take whatever the project produces, intermittency included. Shaped or baseload products cost more but match your consumption better.
Shape is likely to matter more. BloombergNEF reports that the GHG Protocol is revising its Scope 2 guidance, with proposals that could require hourly matching and deliverability requirements. If those proposals are adopted, an annual “100% renewable” claim backed by an as-generated solar PPA could become harder to defend. Hybrid solar-plus-storage deals are one response.
If you’re pricing several offers, ask for every one on the same basis: same term, same settlement point, same REC treatment. Otherwise you’re comparing numbers that don’t measure the same thing.
Keep 20 years of energy contract terms under control
Store every PPA, amendment and notice in one place, with alerts on the dates that carry financial exposure.
How to negotiate the key clauses in a PPA
Developers send their own paper first. Most of it is market standard. The clauses below are where the money and the liability move, so that’s where your redline time goes.
Term, commercial operation date and delay damages
The settlement term usually starts at the commercial operation date (COD), not at signature. A new-build project can take two or three years to get there, which means you’re locked in before the clock even starts.
Negotiate three things:
- A guaranteed COD with a defined cure window.
- Delay damages payable per day or per MW for missed milestones.
- A walk-away right if COD slips past an outside date, with your credit support returned.
Curtailment and negative prices
Curtailment is when the project’s output is reduced, either by the grid operator or by the developer’s choice. In a VPPA, it changes how many MWh you settle and how many RECs you receive.
Watch for “economic curtailment” language. It can let the developer stop generating when market prices go negative, which protects you from paying settlements at a loss. It also cuts your REC volume. Ask for a cap on uncompensated curtailment hours, plus REC replacement or compensation above that cap.
Change in law
A 15-year power purchase agreement will outlive several rounds of energy, tax and carbon accounting rules. The change in law clause decides who pays when the rules shift.
Developer drafting often puts that risk on you. Push for:
- a defined list of qualifying changes
- a cost cap the seller must absorb before any price adjustment
- obligation for the seller to spend up to a negotiated amount to keep the project REC-eligible
- a termination right for you if the environmental attributes lose their value for your reporting
Credit support
Both parties to a power purchase agreement are betting on the other surviving for 20 years. Credit support is how that bet gets secured.
The developer may post a letter of credit before COD and a smaller one during operations. On your side, a common structure is no collateral while you hold an investment-grade rating, with a parent guaranty or letter of credit required if you fall below it. Negotiate the trigger, the posting deadline, and when the support is released, because a ratings downgrade years from now should not unexpectedly become an event of default.
RECs and environmental attributes
For many corporate buyers, RECs are a central reason the deal exists. For a physical PPA, the EPA says that a customer must own the associated project RECs to make green power use claims.
Your contract should specify:
- REC delivery timing and the tracking registry used
- certification, such as Green-e, if your reporting relies on it
- replacement RECs or damages if the project under-delivers
- a ban on the seller selling the same attributes twice
These terms tie directly into your ESG commitments. If you already embed sustainability clauses in energy contracts, align the REC language with them so your claims and your contracts say the same thing.
Termination and early exit
Default termination rights are standard. The negotiation is about cure periods, the events that count as default, and how the termination payment is calculated. In a VPPA, that payment is often a mark-to-market value of the remaining term, which can be a very large number in either direction.
Termination for convenience is uncommon in PPAs and expensive when it exists. If you need flexibility, for example, because of an expected divestiture, negotiate it up front: an assignment right to an affiliate or acquirer or a priced buyout. For the drafting mechanics on notice, cure, and survival, see our guide on how termination clauses work.
Force majeure, assignment and change of control
Force majeure relief in a PPA often excludes events the developer can insure against or should have priced in, such as equipment supply delays. Check that the clause doesn’t double-count with change in law, and set a long-stop date after which either party can terminate.
Assignment matters more than most buyers expect. The project may be refinanced or sold, and lenders may ask you to sign a consent to collateral assignment. Agree on the form of that consent now, so it does not become a bargaining chip for the developer later.
When you redline the developer’s form against your own positions, a clause library helps. DiliTrust’s Risk Detector compares the clauses in a draft to the reference clauses in your library and flags the ones that deviate, so you spend review time on what changed.
Review long-term contracts faster
See how legal teams centralize clauses, approvals and key dates for complex agreements in one contract workspace.
PPA legal review checklist
Before you sign, run the draft through these 10 checks:
PPA review essentials before signature
-
Structure
Confirm whether the PPA is physical or virtual and whether it matches where your load sits.
-
Accounting
Confirm that finance has assessed the potential ASC 815 treatment.
-
Pricing
Check the strike price, escalator, floors or caps, and the settlement point.
-
Commercial operation date
Set the guaranteed COD, delay damages, outside date, and walk-away right.
-
Curtailment
Cap uncompensated hours and require REC replacement above that cap.
-
Change in law
Define the triggers, seller cost cap, and your exit if REC value disappears.
-
Credit support
Set the ratings trigger, posting deadline, and release conditions.
-
RECs
Specify delivery timing, registry, certification, and replacement obligations.
-
Termination
Define default events, cure periods and how the termination payment is calculated.
-
Assignment
Protect affiliate and acquirer rights and agree on the form of lender consent.
How to manage PPA obligations over a 10 to 20 year term
Signing the power purchase agreement is the easy part. The deal now runs longer than most legal team tenures, and the people who negotiated it will likely have moved on before it ends.
Picture an auditor asking, eight years in, whether your company met its credit support obligations after a 2031 ratings downgrade. Or a new CFO asking which PPAs allow assignment in a carve-out. If the answer lives in one person’s inbox, you have a problem.
Build a key-date calendar at signature
List every date with financial or legal consequences on day one: COD milestones, escalator anniversaries, REC delivery deadlines, credit support renewals, letter of credit expiries, and notice windows. Then calculate the action dates. The notice deadline is the date that matters. By the expiry date, it is too late to act.
Assign an owner to every recurring obligation
Each obligation needs a named owner and a reminder that repeats. Finance owns settlement reconciliation. Sustainability owns REC retirement. Legal owns notices, consents and amendments. A structured approach to contract obligation tracking keeps those handoffs visible across teams.
Keep amendments, notices and consents with the contract
Over 20 years, a PPA picks up amendments, lender consents, change in law notices and side letters. Store them with the master agreement. When a dispute arrives, you’ll need to show which version applied on which date.
Report on your PPA portfolio, not single deals
Once you hold three or more PPAs, the risk is in the aggregate: total credit exposure, concentration by developer, and how many contracts share the same change in law trigger. You need to answer those questions in minutes, without rereading each agreement.
This is where contract management software earns its place. With DiliTrust, you keep every PPA, amendment and consent in one secure repository with folder-level access rights. AI suggests key data, such as parties and dates, for the summary sheet, and your team validates the data. Automatic alarms and computed dates, such as a notice deadline calculated from the expiry date minus the notice period, warn the right people before a window closes. For portfolio questions, Smart Reports lets you ask a plain-language question about your contracts and receive a table of results.
For portfolio questions, Smart Reports lets you ask a plain-language question about your contracts and get a results table back. That’s how you answer the new CFO before the meeting ends.
Treat your PPA as a 20-year operating commitment
A power purchase agreement may be a procurement deal for one day, but it creates a legal obligation for the next 10 to 20 years. The structure decides your regulatory and accounting exposure. The clauses decide who pays when prices, rules or projects move. And your post-signature process decides whether anyone notices in time.
Negotiate hard on curtailment, change in law, credit support and RECs. Then build the system that will still know what you agreed when the original deal team is long gone.
Stay in control of every long-term contract
Track key dates, obligations and amendments across your PPA portfolio with alerts your team can act on.
Frequently asked questions
How long does a power purchase agreement last?
Corporate PPAs usually run 10 to 20 years from the commercial operation date. New-build projects add a development and construction period of one to three years before the settlement term starts.
What is the difference between a PPA and a VPPA?
In a physical PPA, you take delivery of the electricity and RECs. In a virtual PPA, the project sells power into the wholesale market and you settle the difference between a fixed strike price and the market price, usually receiving the RECs.
Can a company in a regulated state sign a PPA?
Yes, often through a virtual PPA. Because a VPPA settles financially rather than through physical delivery, your sites may be in a regulated utility territory while the project sits in a competitive wholesale market, subject to the contract structure and applicable rules.
Who owns the RECs in a power purchase agreement?
The contract determines who owns them. Many corporate PPAs transfer the RECs to the buyer, and you generally need to own and retire them to claim the renewable electricity in your reporting.
Is a virtual PPA a derivative?
It can be. VPPAs usually need to be assessed as potential derivatives under ASC 815, which can require mark-to-market accounting. Confirm the treatment with your finance team and auditors before signing.
What happens if a PPA project misses its commercial operation date?
That depends on the contract. Well-negotiated PPAs give the buyer delay damages after the guaranteed COD and a right to terminate, with credit support returned, if the project misses an agreed outside date.